Multi-year stochastic transmission network expansion planning considering line uprating
Author
dc.contributor.author
Álvarez, Ricardo
Author
dc.contributor.author
Rahmann Zúñiga, Claudia Andrea
Author
dc.contributor.author
Cifuentes, Nicolás
Author
dc.contributor.author
Palma Behnke, Rodrigo Ernesto Eduardo
Admission date
dc.date.accessioned
2021-11-15T19:22:56Z
Available date
dc.date.available
2021-11-15T19:22:56Z
Publication date
dc.date.issued
2021
Cita de ítem
dc.identifier.citation
IEEE Access Volume 9, 2021
es_ES
Identifier
dc.identifier.other
10.1109/ACCESS.2021.3061252
Identifier
dc.identifier.uri
https://repositorio.uchile.cl/handle/2250/182692
Abstract
dc.description.abstract
Transmission network expansion planning (TNEP) has become increasingly challenging due to the worldwide transformation of power systems, with the fast deployment of renewable energies as one of the key drivers. Given current socio-environmental concerns, building new lines to integrate new renewable energy sources may take several years and has a significant risk of delays and cost overruns. A sound strategy to achieve a more adapted expansion plan is to include the option of uprating existing lines among planning candidates. This paper presents a novel model for multi-year stochastic TNEP considering line uprating options, such as line reconductoring, voltage uprating, and adding series compensation, along with adding new lines, simultaneously. Compared to adding new lines, line uprating can be performed with low out-of-time service and has lower socio-environmental impact, thus being a cost-effective alternative, especially in cases where acquiring new right-of-ways is difficult and expensive. Illustrative results demonstrate that including line uprating options within the TNEP problem allows us to obtain more economic expansion plans with fewer new line projects in comparison to traditional approaches. This in turn results in less environmental impact of the optimal expansion plan, which makes construction permissions easier to obtain, thus reducing the risk of having delays and cost overruns. Additionally, considering line uprating options also helps the integration of renewable energies by deferring investment decisions until more information regarding future development of renewable energies becomes available.
es_ES
Patrocinador
dc.description.sponsorship
Chilean National Agency for Research and Development ANID/FONDECYT/1201676 ANID/FONDECYT/1181532
ANID/Fondap/15110019
es_ES
Lenguage
dc.language.iso
en
es_ES
Publisher
dc.publisher
IEEE-Inst. Electrical Electronics Engineers
es_ES
Type of license
dc.rights
Attribution-NonCommercial-NoDerivs 3.0 United States