A heuristic approach for scheduling activities with ‘OR’- precedence constraints at an underground mine
Artículo
Access note
Acceso Abierto
Publication date
2020Metadata
Show full item record
Cómo citar
Nancel Penard, Pierre
Cómo citar
A heuristic approach for scheduling activities with ‘OR’- precedence constraints at an underground mine
Author
Abstract
Medium-term development planning of underground mines requires scheduling multiple activities to comply with long-term milestones, and to obtain a time span as short as possible. However, the planning must also respect the availability of construction resources and precedence constraints, which in our case can be disjunctive, that is with more than one alternative predecessor. In this paper, we present an optimisation model to find the schedule of minimum length, satisfying all the constraints mentioned. We develop a heuristic approach to solve it and show that it can be used to produce feasible development plans in a real mine.
Patrocinador
Corporacion de Fomento de la Produccion
16CONTEC-67413
Comision Nacional de Investigacion Cientifica y Tecnologica (CL)
AFB180004
Indexation
Artículo de publicación ISI Artículo de publicación SCOPUS
Quote Item
International Journal of Mining, Reclamation and Environment, marzo 2020
Collections
The following license files are associated with this item: