Increasing the value and feasibility of open pit plans by integrating the mining system into the planning process
Author
dc.contributor.author
Morales, N.
Author
dc.contributor.author
Reyes, P.
Admission date
dc.date.accessioned
2018-03-06T15:29:03Z
Available date
dc.date.available
2018-03-06T15:29:03Z
Publication date
dc.date.issued
2016
Cita de ítem
dc.identifier.citation
The Journel of the Southern African Institute of Mining and Metallurgy, vol. 116: july 2016, p. 663
es_ES
Identifier
dc.identifier.issn
2411-9717
Identifier
dc.identifier.other
10.17159/2411-9717/2016/v116n7a8
Identifier
dc.identifier.uri
https://repositorio.uchile.cl/handle/2250/146717
Abstract
dc.description.abstract
We present a model that allows us to consider mine production scheduling coupled with the mining system at different levels of detail: from the standard origin-destination approach to a network considering different processing paths. Each of these is characterized by variable costs,
capacities, and geometallurgical constraints. We then apply this model to a real mine, comparing the results with those obtained by traditional methodology: the destination of materials defined a priori, before computing the schedules, using standard criteria like cut-off grades. As expected, using optimization to schedule and define dynamically the best processing alternatives shows a big opportunity for potential value improvement. However, the main result is that using only origindestination and fixed cut-off grades may produce schedules that are not feasible when the actual constraints of the mining system are taken into account. Therefore, it is essential to include the considerations proposed in the planning process.
es_ES
Lenguage
dc.language.iso
en
es_ES
Publisher
dc.publisher
The Southern African Institute of Mining and Metallurgy